One of the goals of the FIThydro project is to determine the financial costs of implementing mitigation measures (solutions).
Library of possible measures
|
Min
|
Max
|
Unit
|
[Euro]
|
[Euro]
|
Habitat
|
Instream habitat adjustments
|
Placement of spawning gravel in the river
|
10
|
100
|
per cubic meter
|
Placement of stones in the river
|
50
|
150
|
per cubic meter
|
Cleaning of substrate - ripping, ploughing and flushing
|
1
|
50
|
per square meter
|
Placement of dead wood and debris
|
10
|
150
|
per meter
|
Restoring habitat
|
Removal of weirs
|
2,000
|
1,000,000
|
per weir
|
Construction of a 'river-in-the-river'
|
50
|
5,000
|
per meter
|
Construction of off-channel habitats
|
1
|
100
|
per square meter
|
Shoreline habitat
|
Environmental design of embankments and erosion protection
|
10
|
150
|
per meter
|
Restoration of the riparian zone vegetation
|
1
|
50
|
per square meter
|
Fish migration
|
Downstream
|
Migration barrier removal
|
2,000
|
1,000,000
|
per project
|
Operational measures (turbine operations, spillway passage)
|
NA
|
|
Sensory, behavioural barriers (electricity, light, sound, air-water curtains)
|
NA
|
|
Fish-friendly turbines
|
500,000
|
per turbine
|
Skimming walls (fixed or floating)
|
3,000
|
per m3/second
|
Bypass combined with other solutions
|
10,000
|
25,000
|
per m3/second
|
Fish guidance structures with narrow bar spacing
|
2,000
|
40,000
|
per m3/second
|
Fish guidance structures with wide bar spacing
|
2,000
|
40,000
|
per m3/second
|
Downstream fish protection system using electro shock technique
|
|
|
|
Bottom-type intakes (Coanda screen, Lepine water intake, etc)
|
NA
|
|
Other types of fine screens
|
|
|
|
Vertical slot fishways
|
|
|
|
Upstream
|
Complete or partial migration barrier removal
|
2,000
|
1,000,000
|
per project
|
Nature-like fishways
|
5,000
|
20,000
|
per vertical meter
|
Pool-type fishways
|
10,000
|
100,000
|
per vertical meter
|
Baffle fishways
|
5,000
|
100,000
|
per vertical meter
|
Fishways for eels and lampreys
|
600
|
per meter length
|
Fish lifts, screws, locks, and others
|
10,000
|
500,000
|
per project
|
Truck transport
|
NA
|
|
Sediment
|
Routing
|
Drawdown reservoir flushing
|
1
|
50
|
per cubic meter
|
Sediment sluicing
|
NA
|
|
Removal
|
By-passing sediments
|
NA
|
|
Off-channel reservoir storage
|
NA
|
|
Mechanical removal of fine sediments (dredging)
|
5
|
10
|
per cubic meter
|
Minimizing sediment arrival to reservoir
|
150,000
|
per Vortex tube
|
Restoration in rivers
|
Removal of bank protection
|
NA
|
|
Removal of debris
|
NA
|
|
Environmental flow
|
General flow regime
|
Mitigating reduced annual flow and low flow measures
|
|
|
|
Mitigating reduced flood peaks, magnitudes, and frequency
|
|
|
|
Short-term flow regime
|
Mitigating rapid, short-term variations in flow (hydro-peaking operations)
|
|
|
|