Classification |
Selection
|
Fish species for the measure |
All
|
Does the measure require loss of power production |
Operational (requires flow release outside turbine)
|
-
|
-
|
Recurrence of maintenance |
Yearly
|
Which life-stage of fish is measure aimed at |
-
|
-
|
-
|
Movements of migration of fish
|
Which physical parameter is addressed |
N/A
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
Hydropower type the measure is suitable for |
Plant in dam
|
Plant with bypass section
|
Dam height (m) the measure is suitable for |
Up to 20
|
Section in the regulated system measure is designed for |
In dam/power plant
|
-
|
-
|
-
|
River type implemented |
Steep gradient (up to 0.4 %)
|
Fairly steep with rocks, boulders (from 0.4 to 0.05 %)
|
Slow flowing, lowland, sandy (less than 0.05 %)
|
Level of certainty in effect |
Very uncertain
|
Technology readiness level |
TRL 9: actual system proven in operational environment
|
Cost of solution |
See cost table
|