Difference between revisions of "Costs of solutions"
Jump to navigation
Jump to search
Bendikhansen (talk | contribs) |
Bendikhansen (talk | contribs) |
||
Line 5: | Line 5: | ||
{| class="wikitable" style="text-align:center;" | {| class="wikitable" style="text-align:center;" | ||
|- | |- | ||
− | ! rowspan="2" colspan="3" | Library of possible | + | ! rowspan="2" colspan="3" | Library of possible measures |
! style="vertical-align:middle;" | Min | ! style="vertical-align:middle;" | Min | ||
! style="vertical-align:middle;" | Max | ! style="vertical-align:middle;" | Max | ||
! rowspan="2" style="vertical-align:middle;" | Unit | ! rowspan="2" style="vertical-align:middle;" | Unit | ||
+ | ! rowspan="2" style="vertical-align:bottom;" | Reference | ||
|- | |- | ||
| style="vertical-align:middle;" | [Euro] | | style="vertical-align:middle;" | [Euro] | ||
Line 14: | Line 15: | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="10" | Habitat | | rowspan="10" | Habitat | ||
− | | rowspan="5" | Instream habitat | + | | rowspan="5" | Instream habitat adjustments |
− | | style="text-align:left;" | [[Placement of spawning gravel | + | | style="text-align:left;" | [[Placement of spawning gravel in the river]] |
| 10 | | 10 | ||
| 100 | | 100 | ||
| style="vertical-align:bottom; text-align:left;" | per cubic meter | | style="vertical-align:bottom; text-align:left;" | per cubic meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 1,2 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Placement of stones in the river]] | | style="text-align:left;" | [[Placement of stones in the river]] | ||
Line 24: | Line 26: | ||
| 150 | | 150 | ||
| style="vertical-align:bottom; text-align:left;" | per cubic meter | | style="vertical-align:bottom; text-align:left;" | per cubic meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 3 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style="text-align:left;" | [[Cleaning of substrate - ripping, ploughing and flushing]] | + | | style="text-align:left;" | [[Cleaning of substrate - ripping, ploughing and flushing]] |
| 1 | | 1 | ||
| 50 | | 50 | ||
| style="vertical-align:bottom; text-align:left;" | per square meter | | style="vertical-align:bottom; text-align:left;" | per square meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 3 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Fish refuge under hydropeaking conditions]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Placement of dead wood and debris]] | | style="text-align:left;" | [[Placement of dead wood and debris]] | ||
Line 38: | Line 43: | ||
| 150 | | 150 | ||
| style="vertical-align:bottom; text-align:left;" | per meter | | style="vertical-align:bottom; text-align:left;" | per meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 4 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="3" | Restoring habitat | | rowspan="3" | Restoring habitat | ||
− | | style="text-align:left;" | [[Removal of weirs]] | + | | style="text-align:left;" | [[Removal of weirs]] |
| 2,000 | | 2,000 | ||
| 1,000,000 | | 1,000,000 | ||
| style="vertical-align:bottom; text-align:left;" | per weir | | style="vertical-align:bottom; text-align:left;" | per weir | ||
+ | | style="text-align:right; vertical-align:bottom;" | 5,6 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Construction of a 'river-in-the-river']] | | style="text-align:left;" | [[Construction of a 'river-in-the-river']] | ||
Line 49: | Line 56: | ||
| 5,000 | | 5,000 | ||
| style="vertical-align:bottom; text-align:left;" | per meter | | style="vertical-align:bottom; text-align:left;" | per meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 7 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Construction of off-channel habitats]] | | style="text-align:left;" | [[Construction of off-channel habitats]] | ||
Line 54: | Line 62: | ||
| 100 | | 100 | ||
| style="vertical-align:bottom; text-align:left;" | per square meter | | style="vertical-align:bottom; text-align:left;" | per square meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 8 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="2" | Shoreline habitat | | rowspan="2" | Shoreline habitat | ||
− | | style="text-align:left;" | [[Environmental design of | + | | style="text-align:left;" | [[Environmental design of embankments and erosion protection]] |
| 10 | | 10 | ||
| 150 | | 150 | ||
| style="vertical-align:bottom; text-align:left;" | per meter | | style="vertical-align:bottom; text-align:left;" | per meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 3 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Restoration of the riparian zone vegetation]] | | style="text-align:left;" | [[Restoration of the riparian zone vegetation]] | ||
Line 65: | Line 75: | ||
| 50 | | 50 | ||
| style="vertical-align:bottom; text-align:left;" | per square meter | | style="vertical-align:bottom; text-align:left;" | per square meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 8 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="19" | Fish migration | | rowspan="19" | Fish migration | ||
− | | rowspan=" | + | | rowspan="11" | Downstream |
| style="text-align:left;" | [[Migration barrier removal]] | | style="text-align:left;" | [[Migration barrier removal]] | ||
| 2,000 | | 2,000 | ||
| 1,000,000 | | 1,000,000 | ||
| style="vertical-align:bottom; text-align:left;" | per project | | style="vertical-align:bottom; text-align:left;" | per project | ||
+ | | style="text-align:right; vertical-align:bottom;" | 5,6 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Operational measures (turbine operations, spillway passage) ]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Sensory, behavioural barriers (electricity, light, sound, air-water curtains)]] |
− | | | + | | 800 |
− | | style=" | + | | 4,000 |
+ | | style="vertical-align:bottom; text-align:left;" | per m3/second | ||
+ | | style="text-align:right; vertical-align:bottom;" | 9 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Fish-friendly turbines ]] | | style="text-align:left;" | [[Fish-friendly turbines ]] | ||
| colspan="2" | 500,000 | | colspan="2" | 500,000 | ||
| style="vertical-align:bottom; text-align:left;" | per turbine | | style="vertical-align:bottom; text-align:left;" | per turbine | ||
+ | | style="text-align:right; vertical-align:bottom;" | 10 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style="text-align:left;" | [[Skimming | + | | style="text-align:left;" | [[Skimming walls (fixed or floating)]] |
| colspan="2" | 3,000 | | colspan="2" | 3,000 | ||
| style="vertical-align:bottom; text-align:left;" | per m3/second | | style="vertical-align:bottom; text-align:left;" | per m3/second | ||
+ | | style="text-align:right; vertical-align:bottom;" | 11 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style="text-align:left;" | [[Bypass | + | | style="text-align:left;" | [[Bypass combined with other solutions]] |
| 10,000 | | 10,000 | ||
| 25,000 | | 25,000 | ||
| style="text-align:left;" | per m3/second | | style="text-align:left;" | per m3/second | ||
+ | | style="text-align:right; vertical-align:bottom;" | 12 | ||
|- style="text-align:left; vertical-align:bottom;" | |- style="text-align:left; vertical-align:bottom;" | ||
− | | style=" | + | | style="vertical-align:middle;" | [[Fish guidance structures with narrow bar spacing]] |
− | | style="background-color:# | + | | style="background-color:#FFF;" | 2000 |
− | | style="background-color:# | + | | style="background-color:#FFF;" | 40000 |
− | | style="background-color:# | + | | style="background-color:#FFF;" | per m3/second |
+ | | style="text-align:right;" | 11 | ||
|- style="text-align:left; vertical-align:bottom;" | |- style="text-align:left; vertical-align:bottom;" | ||
− | | style=" | + | | style="vertical-align:middle;" | [[Fish guidance structures with wide bar spacing]] |
− | | style="background-color:# | + | | style="background-color:#FFF;" | 2000 |
− | | style="background-color:# | + | | style="background-color:#FFF;" | 40000 |
− | | style="background-color:# | + | | style="background-color:#FFF;" | per m3/second |
+ | | style="text-align:right;" | 11 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Fish Protection System (induced drift application)]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Bottom-type intakes (Coanda screen, Lepine water intake, etc) ]] |
− | | colspan="2" style="background-color:# | + | | colspan="2" style="background-color:#FFF;" | 17,000 |
− | | style="vertical-align:bottom; background-color:# | + | | style="vertical-align:bottom; background-color:#FFF; text-align:left;" | per m3/second |
− | + | | style="text-align:right; vertical-align:bottom;" | 9 | |
− | | style=" | ||
− | |||
− | |||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Other types of fine screens]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | rowspan=" | + | | rowspan="8" | Upstream |
− | | style="text-align:left;" | [[Complete or partial migration | + | | style="text-align:left;" | [[Complete or partial migration barrier removal]] |
| 2,000 | | 2,000 | ||
| 1,000,000 | | 1,000,000 | ||
| style="vertical-align:bottom; text-align:left;" | per project | | style="vertical-align:bottom; text-align:left;" | per project | ||
+ | | style="text-align:right; vertical-align:bottom;" | 5,6 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Nature-like fishways]] | | style="text-align:left;" | [[Nature-like fishways]] | ||
Line 130: | Line 150: | ||
| 20,000 | | 20,000 | ||
| style="vertical-align:bottom; text-align:left;" | per vertical meter | | style="vertical-align:bottom; text-align:left;" | per vertical meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 13 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Pool-type fishways]] | | style="text-align:left;" | [[Pool-type fishways]] | ||
Line 135: | Line 156: | ||
| 100,000 | | 100,000 | ||
| style="vertical-align:bottom; text-align:left;" | per vertical meter | | style="vertical-align:bottom; text-align:left;" | per vertical meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Baffle fishways]] | | style="text-align:left;" | [[Baffle fishways]] | ||
Line 140: | Line 162: | ||
| 100,000 | | 100,000 | ||
| style="vertical-align:bottom; text-align:left;" | per vertical meter | | style="vertical-align:bottom; text-align:left;" | per vertical meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 5,11,14 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Fishways for eels and lampreys]] | | style="text-align:left;" | [[Fishways for eels and lampreys]] | ||
| colspan="2" | 600 | | colspan="2" | 600 | ||
| style="vertical-align:bottom; text-align:left;" | per meter length | | style="vertical-align:bottom; text-align:left;" | per meter length | ||
+ | | style="text-align:right; vertical-align:bottom;" | 16 | ||
+ | |- style="text-align:left; vertical-align:bottom;" | ||
+ | | style="vertical-align:middle;" | [[Fish lifts, screws, locks, and others]] | ||
+ | | style="background-color:#FFF;" | 10000 | ||
+ | | style="background-color:#FFF;" | 500000 | ||
+ | | style="background-color:#FFF;" | per project | ||
+ | | style="text-align:right;" | 11 | ||
|- style="text-align:left; vertical-align:bottom;" | |- style="text-align:left; vertical-align:bottom;" | ||
− | | style="background-color:#D0CECE;" | | + | | style="vertical-align:middle;" | [[Truck transport]] |
− | | style="background-color:#D0CECE;" | | + | | style="background-color:#D0CECE;" | |
− | | style="background-color:#D0CECE;" | | + | | style="background-color:#D0CECE;" | |
− | | style="background-color:#D0CECE;" | | + | | style="background-color:#D0CECE;" | |
+ | | style="text-align:right; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Vertical slot fishways]] |
− | | | + | | 5,000 |
− | | style=" | + | | 20,000 |
+ | | style="vertical-align:bottom; text-align:left;" | per vertical meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="8" | Sediment | | rowspan="8" | Sediment | ||
Line 160: | Line 193: | ||
| 50 | | 50 | ||
| style="vertical-align:bottom; text-align:left;" | per cubic meter | | style="vertical-align:bottom; text-align:left;" | per cubic meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 15,17 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Sediment sluicing]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="4" | Removal | | rowspan="4" | Removal | ||
− | | style=" | + | | style="text-align:left;" | [[By-passing sediments ]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Off-channel reservoir storage]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style="text-align:left;" | [[Mechanical removal of fine sediments (dredging)]] | + | | style="text-align:left;" | [[Mechanical removal of fine sediments (dredging)]] |
| 5 | | 5 | ||
| 10 | | 10 | ||
| style="vertical-align:bottom; text-align:left;" | per cubic meter | | style="vertical-align:bottom; text-align:left;" | per cubic meter | ||
+ | | style="text-align:right; vertical-align:bottom;" | 15 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| style="text-align:left;" | [[Minimizing sediment arrival to reservoir]] | | style="text-align:left;" | [[Minimizing sediment arrival to reservoir]] | ||
| colspan="2" | 150,000 | | colspan="2" | 150,000 | ||
| style="vertical-align:bottom; text-align:left;" | per Vortex tube | | style="vertical-align:bottom; text-align:left;" | per Vortex tube | ||
+ | | style="text-align:right; vertical-align:bottom;" | 18 | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="2" | Restoration in rivers | | rowspan="2" | Restoration in rivers | ||
− | | style=" | + | | style="text-align:left;" | [[Removal of bank protection]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Removal of debris]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| rowspan="3" | Environmental flow | | rowspan="3" | Environmental flow | ||
− | | rowspan="2" | General flow regime | + | | rowspan="2" | General flow regime |
− | | style=" | + | | style="text-align:left;" | [[Mitigating reduced annual flow and low flow measures ]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
− | | style=" | + | | style="text-align:left;" | [[Mitigating reduced flood peaks, magnitudes, and frequency]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|- style="vertical-align:middle;" | |- style="vertical-align:middle;" | ||
| Short-term flow regime | | Short-term flow regime | ||
− | | style=" | + | | style="text-align:left;" | [[Mitigating rapid, short-term variations in flow (hydro-peaking operations)]] |
| colspan="2" style="background-color:#D0CECE;" | NA | | colspan="2" style="background-color:#D0CECE;" | NA | ||
| style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | | style="vertical-align:bottom; background-color:#D0CECE; text-align:left;" | | ||
+ | | style="text-align:right; vertical-align:bottom; background-color:#D0CECE;" | | ||
|} | |} |
Revision as of 10:56, 30 September 2020
Note: the info on this page is temporary File:Broken
One of the goals of the FIThydro project is to determine the financial costs of implementing mitigation measures (solutions).