Line 12: | Line 12: | ||
=Relevant MTDs and test cases= | =Relevant MTDs and test cases= | ||
− | {{Suitable MTDs for Fish guidance | + | {{Suitable MTDs for Fish guidance structures with wide bar spacing}} |
=Classification table= | =Classification table= | ||
− | {{Fish guidance | + | {{Fish guidance structures with wide bar spacing}} |
=Relevant literature= | =Relevant literature= | ||
[[category:Downstream fish migration measures]][[category:Measures]] | [[category:Downstream fish migration measures]][[category:Measures]] |
Revision as of 12:30, 2 July 2020
Contents
Introduction
Methods, tools, and devices
During planning
During implementation
During operation
Relevant MTDs and test cases
Relevant MTDs | |
---|---|
N/A | |
Relevant test cases | Applied in test case? |
Bannwil test case | - |
Schiffmühle test case | - |
Classification table
Classification | Selection |
---|---|
Fish species for the measure | All |
Does the measure require loss of power production | Operational (requires flow release outside turbine) |
- | |
- | |
Recurrence of maintenance | Yearly |
Which life-stage of fish is measure aimed at | - |
- | |
- | |
Movements of migration of fish | |
Which physical parameter is addressed | N/A |
- | |
- | |
- | |
- | |
- | |
- | |
- | |
Hydropower type the measure is suitable for | Plant in dam |
Plant with bypass section | |
Dam height (m) the measure is suitable for | Up to 20 |
Section in the regulated system measure is designed for | In dam/power plant |
- | |
- | |
- | |
River type implemented | Steep gradient (up to 0.4 %) |
Fairly steep with rocks, boulders (from 0.4 to 0.05 %) | |
Slow flowing, lowland, sandy (less than 0.05 %) | |
Level of certainty in effect | Very uncertain |
Technology readiness level | TRL 9: actual system proven in operational environment |
Cost of solution | See cost table |