Difference between revisions of "Template:Skimming wall (fixed or floating)"
Jump to navigation
Jump to search
(Updating classification tables: Adding FIThydro colors) |
(Updating classification tables: minor changes) |
||
Line 1: | Line 1: | ||
{| class="wikitable" | {| class="wikitable" | ||
− | |||
− | |||
! Classification !! Selection | ! Classification !! Selection | ||
|- | |- | ||
Line 12: | Line 10: | ||
||- | ||- | ||
|- | |- | ||
− | ||Recurrence of maintenance||[[Recurrence of maintenance:: | + | ||Recurrence of maintenance||[[Recurrence of maintenance::Never]] |
+ | |- | ||
+ | |rowspan = "6"|Which life-stage of fish is measure aimed at||- | ||
+ | |- | ||
+ | ||- | ||
|- | |- | ||
− | + | ||- | |
|- | |- | ||
||- | ||- | ||
Line 20: | Line 22: | ||
||- | ||- | ||
|- | |- | ||
− | ||[[Which life-stage of fish is measure aimed at::Movements | + | ||[[Which life-stage of fish is measure aimed at::Movements of migration of fish]] |
|- | |- | ||
− | |rowspan = "8"|Which physical parameter is | + | |rowspan = "8"|Which physical parameter is mitigated||[[Which physical parameter is mitigated::N/A]] |
|- | |- | ||
||- | ||- | ||
Line 44: | Line 46: | ||
||Dam height (m) the measure is suitable for||[[Dam height (m) the measure is suitable for::All]] | ||Dam height (m) the measure is suitable for||[[Dam height (m) the measure is suitable for::All]] | ||
|- | |- | ||
− | |rowspan = "4"|Section in the regulated system measure is designed for|| | + | |rowspan = "4"|Section in the regulated system measure is designed for||- |
|- | |- | ||
− | || | + | ||[[Section in the regulated system measure is designed for::Upstream of hydropower plant]] |
|- | |- | ||
||- | ||- | ||
Line 52: | Line 54: | ||
||- | ||- | ||
|- | |- | ||
− | |rowspan = "3"|River type implemented|| | + | |rowspan = "3"|River type implemented||- |
|- | |- | ||
||[[River type implemented::Fairly steep with rocks, boulders (from 0.4 to 0.05 %)]] | ||[[River type implemented::Fairly steep with rocks, boulders (from 0.4 to 0.05 %)]] | ||
Line 60: | Line 62: | ||
||Level of certainty in effect||[[Level of certainty in effect::Moderately certain]] | ||Level of certainty in effect||[[Level of certainty in effect::Moderately certain]] | ||
|- | |- | ||
− | ||Technology readiness level||[[Technology readiness level::TRL | + | ||Technology readiness level||[[Technology readiness level::TRL 9: actual system proven in operational environment]] |
|} | |} |
Revision as of 12:13, 2 July 2020
Classification | Selection |
---|---|
Fish species for the measure | All |
Does the measure require loss of power production | Operational (requires flow release outside turbine) |
- | |
- | |
Recurrence of maintenance | Never |
Which life-stage of fish is measure aimed at | - |
- | |
- | |
- | |
- | |
Movements of migration of fish | |
Which physical parameter is mitigated | N/A |
- | |
- | |
- | |
- | |
- | |
- | |
- | |
Hydropower type the measure is suitable for | Plant in dam |
Plant with bypass section | |
Dam height (m) the measure is suitable for | All |
Section in the regulated system measure is designed for | - |
Upstream of hydropower plant | |
- | |
- | |
River type implemented | - |
Fairly steep with rocks, boulders (from 0.4 to 0.05 %) | |
Slow flowing, lowland, sandy (less than 0.05 %) | |
Level of certainty in effect | Moderately certain |